Fort Vancouver National Historic Site
North Parking Lot Improvements -Federal project for the National Parks Department-Contract amount $1,436,196 Braun Construction completed this project constructing a new three tier pervious parking lot at the Fort Vancouver Historic Site, a part of the National Park system. The park is a culturally sensitive site and archeological monitoring was required for all excavation and …
Hillsboro Outfall Repair
City of Hillsboro Contract Amount $46,755 Job Summary: Construct/repair sanitary & storm sewer, main and water lines, manholes, cleanouts, catch basins, storm water quality & detention facilities, storm outfalls, adjustment of utility structures to grade, sidewalks, curbs, and street paving.
Water Quality Facility Repair – City Of Tigard
City of Tigard – Greenfield Drive & Ridgefield Lane Water Quality Facility Repair Install storm sewer, retaining wall repair, check dams, swale construction, traffic control and restoration, outfall construction.